Post Hole Concrete Calculator

Calculate the cylindrical hole, subtract the embedded post, multiply by the number of holes, and round concrete bags up.

Your measurements

LIVE
Post-hole concrete orderThe embedded post volume is removed from every cylindrical hole.
39concrete bags
Concrete per hole
2.09 ft³ (0.08 yd³)
Net concrete volume
20.94 ft³ (0.78 yd³)
Order volume
23.04 ft³ (0.85 yd³)
Rounding excess
0.36 ft³ (0.01 yd³)

Post displacement is subtracted. Enter the embedment filled with concrete; this does not choose hole depth or structural capacity.

Show calculationπ × hole diameter² ÷ 4 × depth − post displacement; × 10 holes; round bags up

Transparent method and editable product assumptions. Verify current labels and project requirements.

Tape measure, folding rule, pencil, notes, and construction material samples on a light work surface
Measure the project. Check the product label. Keep the math visible.

How this calculator works

The hole is modeled as a cylinder at the diameter and concrete-filled depth you enter. Gravel bottoms or unfilled tops should be excluded from that depth.

The embedded post volume is subtracted over the same depth. A round post uses a cylinder; a square post uses side × side × depth. The net annular volume is multiplied by the whole number of holes.

Concrete waste is applied once, and finished yield converts volume to whole bags. This workflow intentionally does not choose hole diameter, embedment depth, footing capacity, frost depth, or fence design.

Formula

Net per hole = π × hole diameter² ÷ 4 × depth − post displacement; bags = ceil(total × (1 + waste) ÷ yield)The live substitution appears with your result.

Control example: one 12-inch hole

A 12 in diameter × 36 in deep cylinder is 2.356 ft³ before displacement.

A 4 in round post displaces 0.262 ft³, leaving 2.094 ft³ of concrete per hole.

Assumptions and limits

  • Holes are cylindrical and consistent.
  • Post dimensions are actual embedded dimensions.
  • The entire entered depth is concrete-filled.
  • Bag yield is finished concrete volume from the label.

Common measuring mistakes

  • Forgetting to subtract post displacement.
  • Including a gravel bottom in concrete-filled depth.
  • Using the calculator to choose structural hole dimensions.

Sources

Product-specific values remain editable. These sources support the method and stated examples; they are not a universal substitute for your supplier’s current label.

Questions people ask

Does the calculator subtract the post?

Yes. Select round or square and enter the actual diameter or side.

Should gravel depth be included?

No. Enter only the depth that will actually be filled with concrete.

Does this choose a safe hole depth?

No. Depth and diameter depend on loads, soil, climate, code, and the selected system.